Rabu, 29 November 2017

29 November 2019

Morning Line Up :

Preparation for Volcano Ash

Leader Line Up:
  1. Jati Indah will Start follow up defect list in Mansion 1
  2. If  AS 310 can come today, tomorrow we will sanding Mansion 1 Guest King Gold Ceiling
  3. CARE still continue in Mansion 6
  4. For Jockey ump we will change the power from Booster panel, cause only 20A 3 phase.
 "Saving Energy "
We must make better than before.

Work Activities :

Pak Ayub already come to inspect Mansion1 gold ceiling and will give quotation soon.

AS 310 already come and will do by our CARE team to sanding and sealer the ceiling.

Fire Alarm system already checked by SKJ, tomorrow will continue connect the fire pump alarm to our system.

Check project Gym Mansion 5 with Pak Bambang regarding the AC position.
Already suggested for Re-position for lights.



 Pak Amin already take the wood deckign sample and copclude that that wood not bingkirai.

Selasa, 28 November 2017

28 November 2017

Morning Line Up :

Emergency Action (Volcano)

Leader Line Up :
  1. Test Fire Electric Pump
  2. Cleaning AC in Mansion 2 by Pak Sugeng
  3. Cari in M5 for Sirap and M6 for repaint wall and glass list.

Work Activities :

Check Fire Alarm Panel and Booster pump Spare, there is stil space for the Jockey Pump.

 Repair Leaking Garden Pipe in Mansion 5

 Update Project Gym Mansion 5.









 CARE in Mansion 6.




 Saving Energy in All Mansion : turn off AC from Panel, turn off Lights, pool and pond














 Pool Team never update the board.

Jumat, 17 November 2017

17 November 2107

Morning Line Up :

Sharing and discuss about "work Habits of outsourcing staff". so they can easily work in our Hotels

Work Activities :

Morning Line up discussion
 Update project Gym Mansion 5.