Rabu, 05 April 2017

5 April 2017

Morning Line Up:

Discuss about Water reduce and Eng Goal

Leader Line Up :
  1. Prepare EA M3; Minibar change in master, Chiller fridge Problem will take from Mansion 5, install new sticker in Guest
  2. M5 will request lot of item regarding the Project and defect list walk through.
  3. Inspection in M5

Work Activities :

Take Fridge Control from M5 install in M3






 Repair main door lock, cant lock and difficult to open using the key.

 Check electricity meter and Surge protection.

 Defect list Mansion 5






















 Main Gate mansion broken

 Repair Wood decking in front of master room M2.