"Trip advisor Rank 118"
Leader Line Up :
- Today Fogging in Mansion 1 and 2
- Mansion AC no filter and using Plenum ceiling so many dust in PCB
- CARE will start in Mansion 2
Work Activities :
Meeting With Pak Agus, Pak Eko, Pak Oka, Pak Bambang and Pak Mudana regarding check list and follow up project in Mansion. :
- "Vendor must chasing for BAST, not Operator".
- Check List must do and direct follow up with Engineering Manager and Mansion Manager.
- After Defect and check list follow up and DONE,
- Operator will go Inspection and Give anything suggest and idea to Project leader.
Living terrace M5 that already discolor because the water drop
The water in Planter box M6 so many, has no drain make the ceiling leaking in Bathroom Double
Pool Umbrella already close by HK
But infront of Room not close
Send 7 Umbrella for service
Floor condition in Gym Mansion 5
Type of lights in Gym Mansion 5
This cable need to cut
Pak ANdy ask to chnage the lights and the fitting cause looks ugly
Pak Bambang need to clean this glass from Paint
SKJ team check that the Fire alarm is off and the cable not connected