Rabu, 05 April 2017

5 April 2017

Morning Line Up:

Discuss about Water reduce and Eng Goal

Leader Line Up :
  1. Prepare EA M3; Minibar change in master, Chiller fridge Problem will take from Mansion 5, install new sticker in Guest
  2. M5 will request lot of item regarding the Project and defect list walk through.
  3. Inspection in M5

Work Activities :

Take Fridge Control from M5 install in M3






 Repair main door lock, cant lock and difficult to open using the key.

 Check electricity meter and Surge protection.

 Defect list Mansion 5






















 Main Gate mansion broken

 Repair Wood decking in front of master room M2.


Selasa, 04 April 2017

4 April 2017

Morning Line Up :

Discuss about SOP

Leader Line Up:
  1. Focus On Project in Mansion 5
  2. Make defect list Mansion Walk through in L-Drive Public
  3. Contract maintenance for Lift, Origin and Garden team will end soon. need to review their Work performance.
  4. Prepare EA Mansion 3
Work Activities :

Finishing waterproofing Planter Box brumelia in Mansion 5 and ready to test and fill with water.

 Install lights in Pond Spa





 Plants for Mansion 5 already come.






 Mansion 3 Living terrace drain not really good, need long time to dry the water



 Generator color already change with green color.

Senin, 03 April 2017

3 April 2017

Morning Line Up :
Plan to have Engineering monthly meeting this afternoon.

Leader Line Up :
  1. New CARE Team from Govardan join today for maintenance in Mansion 
  2. Follow Up Mansion 5; repair Spa floor bubbling.
  3. M6 still continue finishing pool deck
  4. Prepare M1
  5. M6 Inspection report did last Saturday.
Work Activities :
M6 Inspection
Hinges kitchen equipment need to repair
Need touch up 
 Light fused  In Living
 Project Insert









 Change termite wood in Master Mansion 6.
 Install stone cover in pole Bale outdoor dining.

 
 
 Still have 2 more Pcs of wood that been eating by termite
 New umbrella install in M3
 


 Update project planter box Brumelia M5