Kamis, 04 Mei 2017

4 May 2017

Morning Line Up :


Leader Line Up :
  1. Fire Hydrant Pilar M5 will Install today by Pak Mudana
  2. Asking CARE in M1 nanny and Pantry.
  3. Organisation chart

Work Activities :

Take pictures of follow up defect list in Master toilet M2
Take pictures of socket that we want to change become USB and International plug.


Hydrant pillar at Mansion 5 already Done By Gitra Mandiri
Do measurement with vendor to do the Gym room at Mansion 5


CARE team repaint car parking Mansion.
Got information from Pande HK, that living terrace floor scrath by monkey.
Pak Herman and Pak Gatot start service the floor colour in Artwork living and bathroom wooden floor at Mansion 1.


CARE team folow up defect list M1.











Turn ON Jockey pump, turn off because change the hydrant pilar in M5 already done.

Take Energy Meter.