Jumat, 11 Agustus 2017

11 August 2017

Morning Line Up :


Learning Coach : remind about learning hours and EID

Leader line Up :
  1. CARE Repair Pool Umbrella
  2. Check Door M1
  3. M5 repair outdoor lighting
  4. Continue check bed smell  in double Mansion 1
ANSUL
Fire System
Hydrant
Garden Lights
Lime Stone Wall
All of them must done in the end of this Month

Fire System repair in Mansion will start 21 August 2017. will do by SKJ with 3 engineer and need one engineering mansion to company the team.

Work Activities :

Finishing Energy room Cost.

Walk through with Pak Kawiers in Mansion 5 :
This Area need to clean from stone and the ladder
 Cut this trees, cause block the view. cut directly by Pak Wayan Garden. the guest arrived but we still doing the trimming inside the Mansion, Butler Atik A little bit upset to Pak kawier because of this.
 Install Extra spot lights for Dinner in Mansion 6 Lower pool area