Senin, 14 Agustus 2017

14 August 2017

Morning Line Up :

Bulgary Villa Preparation

Leader Line Up :
  1. CARE in Mansion 3 to check All the Doors
  2. Will check AC and Drainage in Mansion 3
"Chronic problems need to finish ASAP"
Work Activities :


Meeting With Bu Luna in her Office :
  1. Engineering will do Middle Shift.
  2. Engineering Schedule must be more to prepare.
  3. Fire Data, schedule and report need to attach and send by email to everyone.
  4. Schedule For CARE will come from Pak Dewa.
 Cleaning Sink in Guest Mansion 3 Bathroom

 Garden pipe cut by the garden team
 Check Outdoor AC Mansion 3 "LC" Error appear in Living Area
Found Leaking in outdoor AC in Mansion 3, and directly cleaning the freon, welding the leaking, vacuum and inject new Freon. All done by Pak Sugeng and Pak wantra.