Rabu, 16 Agustus 2017

16 August 2017

Morning Line Up :

Preparation for Independence Day

Leader Line Up:
  1. CARE Continue install liem stone wall and security Post
  2. Focus M5 for Pak Glenn Check In
  3. Remind Pak Andy about Garden Indosekar contract 
Gate each Mansion need to change with Copper, please find quotation and the wheels need to change and all the rail.
Engineering Main job :
  • Saving Energy, Saving Cost
  • Proper Deliver jobs
  • helpin and trust Vendor
" Integrity and Teamwork is the basic of Working "
 Work Activities :

Art Work Pillar Mansion 5 fell down cause of termite.



Change Living terrace Pillar light Mansion 5

Drain Sink in kitchen clogged cause of this waste in Mansion 2.











Check the PO for Buggy R1, Bu Luna ask me to chase the PO